A successful backup job confirms that a job completed. A recovery exercise answers the more useful question: can the application run again with the data and dependencies it needs?
We separate short-term rollback, protection against storage loss and service recovery. Each has a different purpose and should have an owner, a retention policy and a tested procedure.
Use snapshots for a defined rollback point
A VM snapshot is useful before a planned change, but a snapshot that relies on the original storage shares its failure risk. It cannot by itself protect against losing that storage. For databases, also establish whether the captured state is consistent and how the database will recover after restoration.
Keep snapshot retention intentional. Record why a snapshot exists, when it can be removed and how its retained storage is measured. The number of snapshots alone does not describe the space they use.
Put recovery copies in a separate failure domain
Agree where backups live and what loss that destination is meant to survive. Another folder on the same storage is different from a copy at another location. Include the credentials, encryption keys and configuration required to access the backup when the primary environment is unavailable.
Xen Orchestra supports full and incremental backups, replication and several repository types, including S3-compatible storage. These are platform capabilities; the configured destination and retention determine the protection a particular service receives. See the XCP-ng backup documentation.
Define acceptable loss and downtime
The recovery point objective (RPO) describes acceptable data loss. The recovery time objective (RTO) describes the target time to restore service. Choose them with the business before choosing a backup schedule.
Planning example: if losing a day of orders is unacceptable, one overnight backup does not meet the requirement on its own. More frequent protection or database-specific recovery may be needed. The design must then be tested against the agreed target.
Include detection, access, data transfer, restoration, application startup and validation in the recovery timeline. An incident response target is a separate commitment from the time needed to restore a working service.
Restore into an isolated environment
Use a test destination that cannot accidentally send customer notifications, run production schedules or overwrite live data. Restore the database and files, check consistency and test a representative application workflow.
- Record which restore point was used and how long each step took.
- Confirm that an authorized engineer can obtain the required access.
- Check dependencies such as DNS, certificates, object storage and external services.
- Update the runbook when the exercise exposes a missing step.
Agree what is included
Backup frequency, retention, off-site storage, recovery exercises and incident coverage belong in the service scope. A VM price does not establish those commitments. We help define the plan and the evidence needed to show that it works.